Project Timeline - April 13, 2015 - November 19, 2015
Project Scope
Expansion of an existing distribution center
Square Footage
250,000
Equipment Installed
- 16 dock levelers and doors
- 5 50-ton RTUs
- ESFR sprinkler system
Compliance Requirements
Marsh Risk Consulting insurance requirements; local/state building codes
Unique Challenges
The expansion was built during Missouri’s rainy season on the side of the building where the water from the roof drained.
Solutions
We were able to successfully design and install a temporary water management system to capture the run-off water and guide it away from the future building pad to maintain the construction schedule despite the weather.
Results
The temporary drainage system worked, and we were able to avoid weeks of delays that the project would have incurred had we not put the system in place.